Shasta River Bridge Replacement 2009

  • Old Bridge Being Demolished

  • Steel Piles Being Driven for Bridge Foundation

  • New Bridge Members Being Set

  • Completed Construction of the New Bridge

Public Works - Shasta River Bridge Replacement 2009

Project involved the construction of a prestressed deck bulb Tee concrete girder bridge 99.5’ long and 24 feet wide. The existing concrete bridge was removed and the roadway approaches were reconstructed.

The contractor was able to efficiently and safely demolish the existing bridge while working over the Shasta River. The new bridge abutments were built behind the old gravity abutments, which were left for erosion protection.

The girders were erected using two cranes and a launching truss.

 

Project Status: 

Completed

Project Contractor: 

Shasta Services, Inc., dba Timberworks

Project Cost: 

$665,125.35

Public Works Resource Center

Resource Title Downloadable File Type
Encroachment Permit Application - Updated 2017 Download File Permit
Public Works District Map Download File Other
Public Works Snow Removal Policy Download File Policy
Transportation Permit Download File Permit